▪ The HVAC systems on the 4th and 5th floors of Songsim Hall have become outdated due to corrosion and frequent breakdowns, leading to ongoing maintenance issues.
To improve energy efficiency and support the university’s carbon neutrality goals, we will be replacing these aging systems with high-efficiency, eco-friendly HVAC units that help reduce carbon emissions. Noise, dust, and temporary parking restrictions are expected during the HVAC system upgrade on the 4th and 5th floors of Songsim Hall. We kindly ask for your understanding and cooperation.
1. Project: HVAC System Upgrade in Songsim Hall (4th & 5th Floors)
2. Construction Period: Monday, January 20, 2025 – Wednesday, February 19, 2025
3. For any inquiries regarding this project, please contact the Construction Team at Ext. 4882.